Lahntal Bridge Limburg, A3

Short description

Construction of a 450m long bridge.

The project

The two superstructures of the 450 m long and 62 m high Lahntal Bridge each consist of two haunched, longitudinally prestressed hollow girders that were erected in cantilevered cantilevering.

Services in detail

  • 170 t external pre-tensioning
  • 500 t internal pre-tensioning
  • Installation, stressing and injection

 

Procedure:

  • BBV L15
  • BBV L15E